We Have Walls

The bad news: The last ten days have been less exciting.

The good news: Concrete was poured and has cured. Foundation inspection was done Mon 7/18.

The forms were pulled and removed from the site. 

We have footings/foundation/basement walls.

The last few days have been extremely hot/humid. Temps, with the heat index, hit 105. Many folks who work outdoors did not work Thu 7/21 and Fri 7/22.

Gravel was delivered Friday morning…


Next step — backfill. Hopefully that begins tomorrow!